What Should a Property Manager's Lift Station Alarm Plan Include?

Why write the plan before the alarm sounds?

A lift station alarm rarely goes off when the person who knows the station is standing next to it. The plan is written for whoever is there: a leasing agent, a security guard, a new facilities tech.

Arizona's general permit rule for sewage collection systems, A.A.C. R18-9-E301, covers systems that include a lift station serving more than one dwelling. It is a useful checklist even if you are not sure your station operates under it. The rule calls for an audible or visible alarm when sewage in the wet well gets too high or too low, at the wet well site and at the system control center. It also calls for a warning sign on the station with the 24-hour emergency phone number of the owner or operator.

The plan fills in everything between the alarm and the phone number. Our lift station page covers the first minutes after an alarm; this guide covers the sheet you prepare ahead of time.

Who gets the alarm, and who do they call?

Start with how the alarm reaches a person. Some stations only have a light and a horn at the panel, so somebody has to see or hear it. Others also send a signal to an office or a phone. Find out which yours does, and write it at the top of the plan.

Then list the calls in order:

  • The person on the property who takes charge, and a backup for when that person is away.
  • The lift station service company, with the account name and the station's address or location on the site.
  • The owner or asset manager who approves emergency work, and how to reach them after hours.
  • The tenants or building contacts who need to be told to stop running water.
  • The number posted on the station's warning sign. Check that it is still correct; a sign with a former manager's phone number is a common gap.

What should the plan say about water use and access?

When the wet well is filling, every flush and every load of laundry adds to it. The plan should list which buildings or suites drain to the station, so staff know exactly who to ask to hold off on water, and should include a short message that can be sent or posted quickly.

For access, write down what a crew arriving in the dark needs to know:

  • Where the station is, with a simple site map and the nearest gate.
  • Gate codes, and who holds the keys to the control panel and the hatch. The state rule says a lift station is secured to prevent tampering, so a locked station is normal; the plan says who can unlock it.
  • Where a pump truck or service truck can park and how close it can get.
  • Where the electrical disconnect and the panel are, and which breaker feeds the station.

What should staff never do?

Put this in bold on the sheet: nobody on the property staff opens or enters the wet well. Arizona's rule says that operating and maintaining a lift station must follow state and federal confined space entry requirements. OSHA's confined space standard treats a space as permit-required when it contains, or could contain, a hazardous atmosphere, among other dangers. The Arizona rule itself counts lift stations among a collection system's confined space components.

The plan should also say not to silence the alarm and walk away, and not to keep resetting a breaker that trips. Staff can safely do three things: look at the panel from the outside, note what they see, and make the calls.

What should be written down during an alarm?

Keep a blank log page with the plan and record:

  • The date and the time the alarm was noticed, and who noticed it.
  • Which lights were on at the panel and whether either pump was running.
  • Whether power was on at the property.
  • Who was called and when, and when the crew arrived.
  • Whether any sewage came out of the station or backed up into a building, roughly how much, where it went, and whether people were nearby.
  • What the technician found and what was repaired.

Why record a spill so carefully?

Arizona's permit for managing sewage collection systems, R18-9-C305, shows what the state looks at when sewage is released. It treats a release as an imminent and substantial threat when it is more than 2,000 gallons, or more than 50 gallons when, for example, it happened inside an occupied building or reached a public area while people were present.

Whether a release from your property has to be reported depends on your system and its permit, so ask your engineer or the Arizona Department of Environmental Quality. Either way, the volume, the location and who was exposed are the facts everyone will ask for.

What happens when the power goes out?

A lift station cannot pump without electricity. The EPA notes that sewage overflows and bypasses can occur when grid power is lost, and that backup power is not required under the Clean Water Act and is not always required by state law. Arizona's rule calls for a standby power source and redundant level controls on lift stations that receive an average flow of more than 10,000 gallons per day. Smaller stations may have neither.

So the plan needs honest answers to a few questions, checked before monsoon season:

  • Does the alarm still work, and does it still reach someone, when the power is off?
  • Does the station have a generator, or a connection for a portable one? Who brings it and who is allowed to hook it up?
  • If there is no backup power, who is called to pump the wet well down while the power is out?
  • Who checks the station once power returns, and confirms both pumps and the alarm are working again?

How do you keep the plan current?

Review the sheet whenever a manager, vendor or gate code changes, and at least once a year. Ask the technician to confirm at each maintenance visit that the high-level alarm was tested and that both pumps ran.

The second pump matters to the plan. The state rule calls for at least two pumps, with the station able to handle its design flow with any one pump out of service. If a visit finds one pump down, the station has lost its backup, and the plan should treat that as urgent, not as something to schedule later.

Keep a printed copy at the maintenance office, one with the on-call manager, and one with the station's operation and maintenance manual, which Arizona's rule expects to exist and to be kept at a known address.

Common questions

Does Arizona require a lift station to have an alarm?

For sewage collection systems built under the state's 4.01 general permit, yes. A.A.C. R18-9-E301 says excessively high or low sewage levels in the wet well must trigger an audible or visible alarm at the wet well site and at the system control center. If you are not sure which rules apply to an older or private station, ask your engineer or ADEQ.

Can maintenance staff open the wet well to see what is wrong?

No. Arizona's rule requires confined space entry requirements to be followed at lift stations, and OSHA treats a space that could hold a hazardous atmosphere as a permit-required confined space. Staff should look at the control panel from outside, write down what they see and call for service.

Does a lift station need a generator?

Arizona's collection system rule calls for a standby power source and redundant level controls where a lift station receives an average flow of more than 10,000 gallons per day. Smaller stations may not have one, so the alarm plan should say what happens during an outage and who is called to pump the wet well down.

Sources

Get help

Request plumbing service

Tell us the city, the property type, and what you are seeing. We will confirm the cause and the price before work begins.

Call us directly

Call 480-663-2255

Talk with our local team.

Fields marked * are required. Share any other details you have.

Please leave out payment details and passwords.

Add more details (optional)Email, photos, service, and job details

Up to four photos or PDFs, 5 MB each.

Choose a property type to narrow the service list, or leave it blank to see every option.

About the job (optional)
Text messages (optional)

Texts are not required to request or purchase service. This option applies only to texts about One Call Plumbing Services. Read our SMS terms and privacy policy.

By sending, you agree One Call Plumbing Services may call or email you about this request.

Waiting for the online form to load. You can also call 480-663-2255 to request service.

Real customer feedback

Trusted by Arizona customers

5-star feedback from One Call Plumbing Services customers. 4.8 out of 5 from 78 Google reviews (October 2026).

“They were polite, confident and took time to explain the problem and what they were going to do. They had to dig in the grass, but were as least destructive as possible.”

Angie B.Posted on Google, Jan 2023

View on Google (opens in a new tab)